A Cuyahoga County floodplain impact summary dated Nov. 20, 2026, describes plans to replace the Miles Road (C.R. 11) bridge where it crosses the Chagrin River between Chagrin Falls and Moreland Hills. The document identifies the affected area as FEMA Zone AE and lists project ID CUY-Miles Rd (CR11) Bridge 12.10 (PID 125825).

County officials say the current concrete span has deteriorated and is at the end of its usable life, making replacement necessary to keep the roadway safe and reliable. Planned work includes removing an abandoned waterline encased in concrete beneath the bridge, improving approaches, repairing sidewalks and driveways, modifying stormwater drainage, upgrading guardrails, and managing traffic. Construction could begin in September 2028 and is expected to take about nine months.

Because the crossing follows an established road alignment, the county concluded that moving the bridge out of the floodplain was not feasible and that no alternative sites were considered. The summary lists mitigation steps: removing a temporary causeway and restoring river-bottom contours, regrading and seeding disturbed floodplain areas, using erosion and sediment controls, adding rock channel protection, and limiting disturbance to the project area.

A summary signed by Principal Ecologist Len Mikles states that, to his knowledge, the project has complied with applicable local, state, and federal floodplain protection standards. CCDPW is accepting public comments through Dec. 20, 2026, by email at mpastorelle@cuyahogacounty.gov or by mail to Matt Pastorelle, 2079 East 9th Street, Cleveland, OH 44115.