Demolition is underway at 229 Front St. in New Richmond, where a former school bus garage is being removed as the first major phase of a brownfield cleanup, Clermont County announced Nov. 25, 2026. The site is slated to become a public parking lot.

The Clermont County Land Bank, Patriot Engineering, the Village of New Richmond and New Richmond Exempted Village School District secured a $400,000 state brownfield remediation grant for the work. The garage served as the district's bus maintenance and fueling facility from 1986 to 2020. According to the county, soil and groundwater contamination was found after underground diesel tanks were removed, and the district worked with local and state officials on a remediation plan.

Remediation is scheduled for 2027. The parking lot is expected to open late in 2027 or in spring 2028, and Patriot will sample water and monitor the site for two more years.

The county said added parking will support tourism and Front Street businesses. It cited the $13.4 million Liberty Landing riverfront project, completed in October 2026, which includes streetscape improvements and a public marina.