The Ohio Power Siting Board on Nov. 19 approved two natural gas-fired generation projects meant to power nearby data centers, one in Fairfield County and one in Pickaway County, and separately reaffirmed a certificate decision for a Madison County solar project.

In Fairfield County, the board authorized Fairfield Energy Center LLC to build a 1,350-megawatt generating facility and a 1,040-megawatt battery storage system on 122 acres near State Route 37 and State Route 204 in Millersport, southwest of Buckeye Lake. The plant is to serve the Vantage Data Center OH2 campus, planned for up to four data centers on more than 350 acres annexed from Walnut Township. The approval carries 36 conditions, including permits, emergency plans, environmental notice and limits on herbicide use near surface water.

In Pickaway County, PowerConneX Inc. received approval for the 800-megawatt Asheville Energy Center on 110 acres along State Route 752 east of State Route 23. Its 41 conditions include local park and capital contributions, emergency planning, mostly 7 a.m.-to-7 p.m. construction and an on-site environmental specialist in sensitive areas.

The board said both plants are designed to deliver power directly to adjacent data centers rather than through the grid, and that it has no jurisdiction over data center approvals.

Separately, the board reaffirmed that Oak Run Solar Project LLC submitted adequate pictorial sketches or simulations of substation components under the Ohio Administrative Code. The Ohio Supreme Court had remanded that issue. Oak Run involves an 800-megawatt solar facility, two 3½-mile transmission lines and 300 megawatts of storage across Monroe, Somerford and Deercreek townships. The project covers about 4,400 acres within a 6,050-acre area, with parts of the land owned by Bill Gates. A September 2026 board ruling found minimal overall aesthetic impact; on Nov. 19 the board reaffirmed the certificate.